Timeline
Construction Phase 1
24 monthsPhase 2 Start
30 monthsConstruction Phase 2
12 monthsOperating Start
24 monthsModel Horizon
17 yearsEconomics
Inflation Rate
2.5%VAT Rate
24.0%Construction Detail
Conversion
3 monthsDesign & Permit
9 monthsConstruction P1
30 monthsConstruction P2
24 monthsFF&E Install
6 monthsPre-Opening